Caldwell Paving Co. v. GDOT — SR 316 Delay Claim

CriticalActiveLegal hold active

Prime contractor asserts $4.85M in delay and acceleration damages on the SR 316 at Harbins Road interchange project, alleging differing site conditions and untimely utility relocation. GDOT counterclaims for liquidated damages across 84 days.

delay claimconstructiondiffering site conditionsDistrict 1

Current stage

Discovery

Opened Feb 11, 2026 — last activity Sep 30, 2026

Next deadline

Status conference — Fulton Superior

Oct 2, 2026Tomorrow

Exposure

$4,850,000

Brennan, Katz & Moore LLP

Budget to actual

$198,400 of $320,000

Matter details
Everything needed to know where this file stands right now.
Matter number
GDOT-LIT-2026-0148
Matter type
Litigation
Requesting division
Construction
District
District 1 — Gainesville
Court
Superior Court of Fulton County
Judge
Hon. Eleanor Prescott
Opposing party / counsel
Brennan, Katz & Moore LLP
Opened
Feb 11, 2026
Retention schedule
GA-LEG-001 — Litigation Case Files
Recent activity
Status updateSep 30, 2026, 4:20 PM

Received the third supplemental production from plaintiff (6,412 pages). Rolling privilege review underway with Tomas; expect completion by 10/09.

FilingSep 24, 2026, 11:05 AM

Filed Consent Motion to Extend Discovery through 12/18/2026. Court granted the same day, and every downstream deadline was recalculated automatically in the matter calendar.

NoteSep 18, 2026, 9:40 AM

Scheduling conflict: the Pinnacle expert deposition and the Thompson trial calendar both fall the week of 11/16. Recommend moving Pinnacle to 11/30.

Related contracts